Achieved Projects

Saida 01
18/06/2019
Commissioning of the new primary substation by the extension of 24 new MV cables.
View Album

Nabatieh 01 & 02
31/12/2018
Extension of 4 new MV feeders from Nabatieh primary substation to reduce the load on Yohmor, Choukeen, Jebshit & Taamir MV feeders.

Zahrani 01
31/12/2018
Supply transfer of Taplain and Raissi MV feeders from Msayleh to Zahrani primary substations to reduce the load on the 66kV grid.
View Album

Sour 02
31/03/2019
Reinforcement of Abassayeh and Hamadieh MV feeders supplied from Sour primary substation.
View Album
Jowaya 01
30/06/2019
Extension of 2 new MV feeders from Soultanieh primary substation to reduce the load on Chehabieh and Chakra MV feeders in addition to the reinforcement of Sawaneh MV feeder and extension of 3 new reserve MV cables for future use.
View Album
Sour 01
31/03/2019
Reinforcement of Aytit MV feeder, supply transfer of Qana MV feeder from Soultanieh to Wadi Jilou primary substations and creation of 15kV medium voltage link between Wadi Jilo and Soultaniah primary substations required by EDL.

Sour 03
8/9/2020
Extension of six new MV feeders from Sour primary substation to reduce the load south of Sour area while reinforcing the existing ones.
View Album
Jezzine 01
15/10/2020
Restructuring and reinforcement of number 1 & 3 MV feeders supplied by Awwali primary substation in preparation for the planned HV/MV primary substation in Jezzine area.
View Album
Marjeyoun 01
30/09/2019
Reinforcement of Marjeyoun and Kfarkela MV feeders supplied from Marjeyoun primary substation

Zahrani 02
31/12/2019
Extention of a new MV feeder from Msayleh primary substation while reinforcing & restructuring of Radar, Aaqtanit, Zefta & Marwanieh MV feeders.
View Album
Hasbaya 01
11/6/2020
Reinforcement and load reduction on Chebaa & Hasbaya MV feeders supplied from Marjeyoun primary substation by the extention of one new MV feeder.

Nabatieh 03
15/12/2020
Load reduction on Habboush & Kfarouman MV feeders by the extention of two new MV feeders from Nabatieh primary substation and four additional new reserve cables for future use.
View Album